11/14 - Monday -Fire Sprinkler Rough, Insulate Fire Sprinkler Lines, Pipe Collars/Roof Boots, Electric Rough
11/15 - Tuesday - Electric Rough, Inspect Gas/Plumbing, Structured Wiring
11/16 - Wednesday - Air Seal, Trench Inspection, Brick
11/17 - Thursday - Meter Base, Brick,
11/18 - Friday - Concrete Stoop, Brick, Deck Bandboard, Inspect Electric
Here was the actual schedule:
We went to the house on Tuesday and Thursday of this week. We did get our plumbing rough and electric rough. Better seen with the pictures below :)
But before we get to the pictures, let's talk about how my neighbor found out that the contractors were pissing in our house instead of using the provided porta potties. On the night of the 17th, I get the following pictures from my neighbor showing wet pee in the basement. He said that the urine smell was bad as well. He e-mailed the lead contractor and let him know how unacceptable this was and that he wanted to know how this was going to be taken care of. I was not expecting that he was going to do much, but the e-mail back was surprising. He fired the crew that was there and was going to send a cleaning crew out the next day. I seriously did not think we would ever have to deal with all of this BS!
Now onto the weekly pictures.
11/15 - Tuesday - Electric Rough, Inspect Gas/Plumbing, Structured Wiring
11/16 - Wednesday - Air Seal, Trench Inspection, Brick
11/17 - Thursday - Meter Base, Brick,
11/18 - Friday - Concrete Stoop, Brick, Deck Bandboard, Inspect Electric
Here was the actual schedule:
We went to the house on Tuesday and Thursday of this week. We did get our plumbing rough and electric rough. Better seen with the pictures below :)
But before we get to the pictures, let's talk about how my neighbor found out that the contractors were pissing in our house instead of using the provided porta potties. On the night of the 17th, I get the following pictures from my neighbor showing wet pee in the basement. He said that the urine smell was bad as well. He e-mailed the lead contractor and let him know how unacceptable this was and that he wanted to know how this was going to be taken care of. I was not expecting that he was going to do much, but the e-mail back was surprising. He fired the crew that was there and was going to send a cleaning crew out the next day. I seriously did not think we would ever have to deal with all of this BS!
Pee!
More Pee!
Basement was cleaned.
Plumbing for out sink.
Fun looking plumbing for our refrigerator.
Maze of plumbing in the ceiling.
Powder room plumbing.
Extra bath.
Shower
My soaking tub <3
Recessed lights added to the living room.
Crazy amount of recessed lights added to the kitchen.
Washer/Dryer setup
Electric running in the bedrooms. Lights and smoke detectors.
Master bedroom